Live blog new building

16-01: Progress of the new building

After the holidays, the builders immediately started working on the inside of the building. The interior walls on the third floor have been placed. In the coming period they will also install the interior walls on the other floors. The parking garage and the industrial building will also be further finished.

20-12: Progress of the new building

This week the builders finished the cement screed in the office area. The overhead doors are also placed on both sides of the industrial hall. Inside, the builders have prepared the underfloor heating. If all goes well, the siding will be finished today. The interior walls will be installed in January 2020. Work is done from top to bottom. See you in 2020!

13-12: Progress of the new building

Last week the builders continued to pour the concrete into the industrial hall. This should dry well in the coming period. In addition, they have also started installing all the windows in the building. The large glass front is now closed. This will soon bring a beautiful light to the demo room. The industrial hall is also further insulated and the finishing plates are placed.

05-12: Progress of the new building

This week, the builders continued to finish the wall where large windows come in. They have also poured the first half of the concrete and have been busy deepening the concrete until deep into the night. This piece remains unreachable for the time being because it needs to dry well. Next Thursday they will start working on the second piece of concrete in the hall. In addition, they are entering the second phase of installing floor heating in the offices.

29-11: Progress of the new building

Last week the roofing was installed and the shed roofs were also installed. These special roofs provide extra daylight in the spacious hall. A start will be made with the glass wall next week. This is the large glass in front of the experience room where our machines will soon be exhibited. First the frames are placed for this. They will also make a start with the pouring of the concrete floor in the industrial hall. They will also immediately put a special coating on the floor, making this part of the hall unreachable because it needs to dry.

22-11: Progress of the new building

This week a start has been made with the floor heating in the industrial hall and this is expected to be ready next week. Over 16 km of floor heating will be installed. In addition, it is clear from the outside that the white cladding is beautiful. You can clearly see the definitive colors and appearance of the building. They are also completely finished with all the masonry and the scaffolding is demolished. The side of the parking garage and storage is now slowly becoming visible. The window frames of the office area will also be placed very soon.

15-11: Progress of the new building

The building was completely closed last week (except for the windows). In the coming weeks they will be working hard with the sewer and the water connections. They have also started to cover the office part. In addition, everything is well insulated, after which another layer is placed. Before the Christmas holidays, they try to finish this work and pour the first concrete for the floors.

08-11: Progress of the new building

This week a major step has been taken in making the building windproof and waterproof. The roof plates have been placed and the sides of the hall have also been placed. The ‘holes’ in the roof for extra daylight in the assembly hall are now also clearly visible. The brickwork for parking garage, warehouse and roof terrace is almost ready and the office area follows quickly.

01-11: Progress of the new building

This week the construction workers completed the steel construction and the last piles for the foundation were drilled under the hall. The complete shape of the hall is now visible. In addition, they have already installed the nets for fall protection during the placement of the roof plates. The steel roof plates and rainwater drainage will be fitted next week.

25-10: Progress of the new building

04-10: Progress of the new building

23-09: Progress of the new building

13-09: Progress of the new building

05-08: Progress of the new building

02-08: Progress of the new building

26-07: Progress of the new building

28-06: Progress of the new building

19-06: Progress of the new building

The offices will be placed on the right-hand side of the building. The foundation for the parking garage and storage is already visible on the left. Between these two ‘towers’ is the experience room where everyone will soon be able to test and experience our machines. The highest point is expected around the building trade.

21-05: Progress of the new building

17-04: Progress of the new building